Recon in Progress
| Project preparation | $2,119 |
|---|---|
| Searching for already converted records: Estimate ~10% already converted (series), leaving ~18,000 titles to convert (students $5.65/hour; 1 shelflist drawer ~25 hours of work) | |
| OCLC costs | $50,635 |
|
Conversion $2.45/record Auth. control $0.06/record Output $0.29/record + $235 annual fee |
|
| Barcoding | $6,912 |
| $0.32/volume (estimated volume : title ratio = 1.2 : 1) |
|
| Post conversion authority & bibliographic work | $29,829 |
| 1.25 FTE Band C for 9 months ... $28,852 0.25 FTE student for 4 months ... $977 (Band C year 2000/01 $30,775.51; student $5.65/hour) |
|
| Barcode cleanup | $7,694 |
| 0.50 FTE Band C for 6 months (Band C year 2000/01 $30,775.51) This may not be done until 1 yr + later. |
|
| Supplies | $500 |
| Contingency | $2,311 |
|
TOTAL |
$100,000 |
We asked the South Central Regional Library Council to support this project financially via the 2001 Regional Automation Program grant. We have received $10,000 for this project.
Prepared by Hana Dedina (CTS Cataloging)
February 2001
Recon in Progress